ContID 252008 EST NO 0006 |
Date:06/18/2025 |
COMMONWEALTH OF KENTUCKY
TRANSPORTATION CABINET
Contract ID | 252008 | Estimate Number | 0006 | Estimate Type | DRAFT_PROGRESS | ||
District Office | SOMERSET (08320) Taylor, Tracy J. | ||||||
Contractor | OGLESBY CONSTRUCTION INC | MARS ADDR SN 0 | |||||
1600 TOLEDO RD RT 20 WEST | |||||||
PO BOX 380 | |||||||
NORWALK , OH , 44857 | |||||||
Pay Period | 05/31/2025 TO 06/13/2025 | ||||||
Date Approved | 06/17/2025 | ||||||
Primary Proj Number | MP12100002508 | ||||||
Project No. | FE01 121 DW25 0080000 | ||||||
Primary County | VARIOUS | ||||||
Name of Road | VARIOUS ROUTES IN DISTRICT 8 | ||||||
Description | VARIOUS ROUTES IN DISTRICT 8. | ||||||
Date Let | 02/20/2025 | Formal Acceptance | |||||
Date Awarded | 03/04/2025 | Date Work Began | |||||
Date Contract Executed | 03/06/2025 | Open To Traffic | |||||
Date NTP Issued | 03/06/2025 | Actual Completion Date | |||||
Current Contract Amount | $1,390,443.58 |
Total to Date |
Prev to Date |
This Estimate |
||
Original Amount | $1,390,443.58 |
Total Earnings | $663,786.13 |
$500,095.56 |
$163,690.57 |
|
Percent Complete | 47.74 |
Stockpiled Materials | $0.00 |
$0.00 |
$0.00 |
|
Funds Available | $726,657.45 |
Gross Earnings | $663,786.13 |
$500,095.56 |
$0.00 |
|
Total Change Orders | $0.00 |
Other Adjustments | $0.00 |
$0.00 |
$0.00 |
|
TOTAL | $663,786.13 |
$500,095.56 |
163,690.57 |
|||
Contract Id | 252008 | Change Order Summary |
County | VARIOUS | ||||||
Estimate Nbr | 0006 | Project Number | FE01 121 DW25 0080000 | |||||||
Contractor | OGLESBY CONSTRUCTION INC | Period | 05/31/2025 TO 06/13/2025 | |||||||
CHANGE ORDERS HISTORY | ||||||||||
CHANGE ORDER NBR | DESCRIPTION | STATUS | APPROVAL DATE | TOTAL CO AMOUNT | CONTRACT TIME ADJUSTED | |||||
CONTRACT ADJUSTMENTS HISTORY
Contract Adjustments |
|
|
Adjustment Description | Est No |
Adjustment Amount |
Line Item Adjustments History | |||||||||
PROJECT | ITEM NBR | DESCRPITION | TYPE | EST NO | ADJ QUANTITY |
UNIT PRICE |
ADJUSTED AMOUNT |
Contract Id | 252008 | COMMONWEALTH OF KENTUCKY |
County | VARIOUS | ||||||
Contract Type | TRWB WATERBOURNE PAINT STRIPING | TRANSPORTATION CABINET |
Primary Project Number | MP12100002508 | ||||||
Estimate Nbr | 0006 | Period | 05/31/2025 TO 06/13/2025 | |||||||
Contractor | OGLESBY CONSTRUCTION INC | |||||||||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | ||||||||
LINE ITEM NUMBER | ITEM DESCRIPTION | ITEM NO. | UNIT | PLAN QTY | CURRENT QUANTITY | QUANTITY PAID THIS EST | QUANTITY PAID PREV. EST | QUANTITY PAID TO DATE | UNIT PRICE | AMOUNT PAID THIS EST | AMOUNT PAID TO DATE | |
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0000 OVERALL CONTRACT ITEMS | |||||||
0005 | QUALITY CONTROL | 02572 | LS | 1.00 | 1.000 | 0.200 | 0.400 | 0.600 | 28,000.00 | 5,600.00 | 16,800.00 | |
0010 | MAINTAIN & CONTROL TRAFFIC | 02650 | LS | 1.00 | 1.000 | 0.800 | 0.800 | 43,500.00 | 34,800.00 | |||
0015 | LAW ENFORCEMENT OFFICER | 20411ED | HOUR | 8.00 | 8.000 | 0.000 | 0.000 | 100.00 | 0.00 | |||
0020 | WATER BLASTING EXISTING STRIPE | 22664EN | LF | 250.00 | 250.000 | 0.000 | 0.000 | 3.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0001 ADAIR COUNTY RURAL SECONDARY ROUTES | |||||||
0025 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES ADAIR 50% INITIAL | 06520 | MILE | 23.88 | 23.882 | 23.531 | 23.531 | 262.50 | 6,176.88 | |||
0027 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES ADAIR 50% FINAL | 06520 | MILE | 23.88 | 23.882 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0030 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES ADAIR 50% INITIAL | 06521 | MILE | 47.15 | 47.150 | 40.218 | 40.218 | 280.00 | 11,261.04 | |||
0032 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES ADAIR 50% FINAL | 06521 | MILE | 47.15 | 47.150 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0023 CASEY COUNTY RURAL SECONDARY ROUTES | |||||||
0035 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CASEY 50% INITIAL | 06520 | MILE | 2.92 | 2.928 | 2.904 | 2.904 | 262.50 | 762.30 | |||
0037 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CASEY 50% FINAL | 06520 | MILE | 2.92 | 2.928 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0040 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CASEY 50% INITIAL | 06521 | MILE | 47.43 | 47.436 | 58.290 | 58.290 | 280.00 | 16,321.20 | |||
0042 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CASEY 50% FINAL | 06521 | MILE | 47.43 | 47.436 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0027 CLINTON COUNTY RURAL SECONDARY ROUTES | |||||||
0045 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CLINTON 50% INITIAL | 06520 | MILE | 22.98 | 22.989 | 21.195 | 21.195 | 262.50 | 5,563.68 | |||
0047 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES CLINTON 50% FINAL | 06520 | MILE | 22.98 | 22.989 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0050 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CLINTON 50% INITIAL | 06521 | MILE | 51.14 | 51.142 | 42.928 | 42.928 | 280.00 | 12,019.84 | |||
0052 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CLINTON 50% FINAL | 06521 | MILE | 51.14 | 51.142 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0029 CUMBERLAND COUNTY RURAL SECONDARY ROUTES | |||||||
0055 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CUMBERLAND 50% INITIAL | 06521 | MILE | 41.68 | 41.682 | 37.460 | 37.460 | 280.00 | 10,488.80 | |||
0057 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES CUMBERLAND 50% FINAL | 06521 | MILE | 41.68 | 41.682 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0069 LINCOLN COUNTY RURAL SECONDARY ROUTES | |||||||
0060 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LINCOLN 50% INITIAL | 06520 | MILE | 23.33 | 23.330 | 55.995 | 55.995 | 262.50 | 14,698.68 | |||
0062 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES LINCOLN 50% FINAL | 06520 | MILE | 23.33 | 23.330 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0065 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LINCOLN 50% INITIAL | 06521 | MILE | 34.01 | 34.018 | 55.855 | 55.855 | 280.00 | 15,639.40 | |||
0067 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES LINCOLN 50% FINAL | 06521 | MILE | 34.01 | 34.018 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0074 McCREARY COUNTY RURAL SECONDARY ROUTES | |||||||
0070 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES MCCREARY 50% INITIAL | 06520 | MILE | 29.31 | 29.312 | 18.161 | 18.161 | 262.50 | 4,767.26 | |||
0072 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES MCCREARY 50% FINAL | 06520 | MILE | 29.31 | 29.312 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0075 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES MCCREARY 50% INITIAL | 06521 | MILE | 40.33 | 40.338 | 27.327 | 27.327 | 280.00 | 7,651.56 | |||
0077 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES MCCREARY 50% FINAL | 06521 | MILE | 40.33 | 40.338 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0100 PULASKI COUNTY RURAL SECONDARY ROUTES | |||||||
0080 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES PULASKI 50% INITIAL | 06520 | MILE | 96.80 | 96.806 | 46.221 | 0.000 | 46.221 | 262.50 | 12,133.01 | 12,133.01 | |
0082 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES PULASKI 50% FINAL | 06520 | MILE | 96.80 | 96.806 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0085 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES PULASKI 50% INITIAL | 06521 | MILE | 170.09 | 170.095 | 133.288 | 80.708 | 213.996 | 280.00 | 37,320.64 | 59,918.88 | |
0087 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES PULASKI 50% FINAL | 06521 | MILE | 170.09 | 170.095 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0102 ROCKCASTLE COUNTY RURAL SECONDARY ROUTES | |||||||
0090 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES ROCKCASTLE 50% INITIAL | 06521 | MILE | 33.18 | 33.188 | 33.166 | 33.166 | 280.00 | 9,286.48 | |||
0092 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES ROCKCASTLE 50% FINAL | 06521 | MILE | 33.18 | 33.188 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0104 RUSSELL COUNTY RURAL SECONDARY ROUTES | |||||||
0095 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES RUSSELL 50% INITIAL | 06520 | MILE | 1.80 | 1.806 | 1.652 | 1.652 | 262.50 | 433.65 | |||
0097 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES RUSSELL 50% FINAL | 06520 | MILE | 1.80 | 1.806 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0100 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES RUSSELL 50% INITIAL | 06521 | MILE | 23.55 | 23.558 | 21.999 | 21.999 | 280.00 | 6,159.72 | |||
0102 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES RUSSELL 50% FINAL | 06521 | MILE | 23.55 | 23.558 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0116 WAYNE COUNTY RURAL SECONDARY ROUTES | |||||||
0105 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES WAYNE 50% INITIAL | 06520 | MILE | 48.14 | 48.144 | 5.885 | 48.892 | 54.777 | 262.50 | 1,544.81 | 14,378.96 | |
0107 | PAVE STRIPING-WB PAINT-4 IN W RS ROUTES WAYNE 50% FINAL | 06520 | MILE | 48.14 | 48.144 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0110 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES WAYNE 50% INITIAL | 06521 | MILE | 88.21 | 88.218 | 5.915 | 107.688 | 113.603 | 280.00 | 1,656.20 | 31,808.84 | |
0112 | PAVE STRIPING-WB PAINT-4 IN Y RS ROUTES WAYNE 50% FINAL | 06521 | MILE | 88.21 | 88.218 | 0.000 | 0.000 | 280.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0121 STATE PRIMARY, STATE SECONDARY, & SUPPLEMENTAL ROUTES | |||||||
0115 | PAVE STRIPING-WB PAINT-4 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06520 | MILE | 288.73 | 288.739 | 66.225 | 164.236 | 230.461 | 262.50 | 17,384.06 | 60,496.01 | |
0117 | PAVE STRIPING-WB PAINT-4 IN W STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06520 | MILE | 288.73 | 288.739 | 0.000 | 0.000 | 262.50 | 0.00 | |||
0120 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% INITIAL | 06521 | MILE | 303.92 | 303.921 | 78.148 | 143.198 | 221.346 | 280.00 | 21,881.44 | 61,976.88 | |
0122 | PAVE STRIPING-WB PAINT-4 IN Y STATE SECONDARY & SUPPLEMENTAL ROUTES VARIOUS 50% FINAL | 06521 | MILE | 303.92 | 303.921 | 0.000 | 0.000 | 280.00 | 0.00 | |||
0125 | PAVE STRIPING-WB PAINT-6 IN W STATE PRIMARY ROUTES VARIOUS 50% INITIAL | 06522 | MILE | 352.03 | 352.032 | 75.508 | 282.175 | 357.683 | 362.50 | 27,371.65 | 129,660.08 | |
0127 | PAVE STRIPING-WB PAINT-6 IN W STATE PRIMARY ROUTES VARIOUS 50% FINAL | 06522 | MILE | 352.03 | 352.032 | 0.000 | 0.000 | 362.50 | 0.00 | |||
0130 | PAVE STRIPING-WB PAINT-6 IN Y STATE PRIMARY ROUTES VARIOUS 50% INITIAL | 06523 | MILE | 339.14 | 339.149 | 99.484 | 209.703 | 309.187 | 390.00 | 38,798.76 | 120,582.93 | |
0132 | PAVE STRIPING-WB PAINT-6 IN Y STATE PRIMARY ROUTES VARIOUS 50% FINAL | 06523 | MILE | 339.14 | 339.149 | 0.000 | 0.000 | 390.00 | 0.00 | |||
Project | MP12100002508 | Fed/State Project Number | FE01 121 DW25 0080000 | Category | 0125 DEMOBILITATION | |||||||
0135 | DEMOBILIZATION | 02569 | LS | 1.00 | 1.000 | 0.000 | 0.000 | 22,000.00 | 0.00 | |||
SUBTOT | $163,690.57 |
$663,786.120 |
||||||||||
LNNBR | STOCKPILE ADJUSTMENTS | UNIT |
ADJ. QUANTITY |
EST NBR |
UNIT PRICE | ADJUSTED AMOUNT |
||||||
SUBTOT | 0.00 |
$0.000 |